I questioned the Snowy Hydro Authority on the Snowy 2.0 project at Senate Estimates.

Snowy 2.0 is a ‘big battery’ that pumps water from the Talbingo Reservoir up to the Tantangara Reservoir during the day when there is excess wind and solar electricity, then lets the water down during the evening peak to generate electricity when the sun isn’t shining and wind isn’t blowing.

If this sounds like we are planning on generating electricity twice to use it once, that is exactly what pumped hydro does.

The original cost of $2 billion is now out to $5.9 billion and likely to go over $10 billion. In addition, the transmission lines to bring the power into the grid will gouge out national parks and farmland, and cost another $10 billion. And their main boring machine has been bogged for more than a year.

I asked if this project is worth continuing.

The lack of detail around how much the power will cost electricity customers is frightening.

Listen to the answers. It sounds like the Snowy Authority is planning to profiteer by having the only power available when solar and wind are not generating enough power.

All I can say is be worried – this Government is actively planning massive increases in power bills.

Transcript

Senator Roberts: Thank you for appearing again today. Florence is now acknowledged to be bogged. When will it be unbogged?

Mr Barnes: I expect in weeks, not months. As soon as the slurry plant is operating, we’ll push forward, obviously in close consultation with our colleagues at DPIE and Parks, but we expect it to be relatively soon.

Senator Roberts: I empathise with you, having managed underground projects, some quite large—not as large as this one. There is a lot of uncertainty, and it’s hard telling people who are looking on how to think about this. It’s very difficult to describe.

Mr Barnes: You’ve got to see it to believe it.

Senator Roberts: That’s right. We’ve got journalists—admittedly journalists—now saying it’s time to cut our losses on Snowy 2.0. If the project is completed and all the high-voltage transmission lines are built across farmyards and national parks, there must be a calculation that takes the capital cost of the project as a whole and divides that by the life of the project to get a figure for how much the annual amortisation charge for the capital costs will be. Do you have the latest projection, please?

Mr Barnes: There was quite a lot in your question. Obviously we haven’t got an updated cost here, and we’ll provide that in months. We don’t have the cost of transmission, so I wouldn’t be able to provide that. I fully expect, through our corporate plan process, we’ll assess the returns from Snowy 2.0, and, if anything, the commercial case for it has got stronger since FID.

Senator Roberts: Sorry?

Mr Barnes: The commercial case for it has gotten stronger since the financial investment decision.

Senator Roberts: There were many factors that drove that commercial decision in the first place. Well, it wasn’t commercial, from what we understand, because there was no cost-benefit analysis, and the business case was redacted heavily, under Malcolm Turnbull’s prime ministership. This annual amortisation charge, which you can’t provide, is combined with annual costs like labour and maintenance to calculate what the real cost per megawatt hour will be once the project starts. You wouldn’t have the projected cost per megawatt hour either then?

Mr Barnes: That’s correct, but to think about Snowy 2.0 in megawatt hours is perhaps not the right way to think about it.

Senator Roberts: It’s a battery.

Mr Barnes: Yes, but it’s the provision of dispatchable demand over very long storage duration that allows lots of variable renewable electricity to be delivered. So we look at the business case in a much more fulsome way across the whole Snowy business. For example, over the past few years, we’ve procured 1,500 megawatts of solar and wind PPAs to enable the transition, which assets like Snowy 2.0 support. I think you’ve got to look at a whole-of-business business case, and the simple amortisation plus labour is, perhaps, too simplistic a way to consider the business case.

Senator Roberts: Now you’ve got me really worried. It’s not your responsibility with the solar and wind, but now I’m terrified of it. Your website lists the levelised cost of storage at between $25 and $35 per megawatt hour. On 340,000 megawatt hours each year, this suggests an annual cost of $11 million, including operating costs, maintenance, capital costs and the cost of buying the electricity to pump the water uphill. Is the $25 to $35 figure still accurate and, if not, what is the new figure?

Mr Barnes: I’ve not got a calculator that capable in my head, but I think there might be a multiplying factor out on those numbers. The levelised cost of storage I think we have on our website is sourced from international studies and our view of levelised cost of storage. I don’t have the updated figure in my head at the moment.

Senator Roberts: Our staff team did some calculations. Now, admittedly, we don’t have all the costs, but it just seems ridiculously low. When we pile on these extra costs of the delay, we’re wondering about what will happen.

Mr Barnes: Just to be clear, the levelised cost of storage is what one would add to variable renewable electricity to provide a firm product. Also, the 340,000 megawatt hours of storage is not deployed over a year. It will be deployed multiple times through the year, depending on the market dynamics.

Senator Roberts: It seems to us that the capital cost is becoming a huge stumbling block. Even if you take just the cost of the project, at $6 billion—and there are serious doubts about that now—and amortise those across 50 years, the annual capital charge will be $120 million, and double that if you add the pole and the wires. That puts the cost of your electricity at over $700 per megawatt per hour, including the poles and wires. The current spot price for last weekend—admittedly the weekend was cold down here—for last weekend was $150 per megawatt hour. Is there something we’re missing?

Mr Barnes: We’ll certainly do a full financial review of the project when the increased costs are known. But I think you’re mischaracterising the nature of the asset in that it isn’t an energy provider. It’s an insurance provider for when the wind isn’t blowing, the sun isn’t shining or there is plant failure elsewhere. So we don’t sell it as a baseload energy price, which is what you’re referencing.

Senator Roberts: Hasn’t it been touted as a peak period source of electricity?

Mr Barnes: The two major sources of revenue will be the difference between the price we pump the water up to Tantangara, which will soak up demand from solar and wind when it’s not required, and the price at which we sell it in peak periods when solar and wind aren’t available or other plants are not available. So it’s an asset about being there when everything else isn’t. It isn’t sold on an energy basis, which are the reference prices you’re quoting.

Senator Roberts: Okay. But the projected cost must be the single most important KPI of this project.

Mr Barnes: Cost and schedule are my most important KPIs. The reason we came out with the schedule is that there are many stakeholders interested in the schedule, and we’ll work through the cost and associated business plans around that.

Senator Roberts: There seems to be a real risk, though. I acknowledge your point that we can’t just charge per kilowatt hour—or we can’t just recognise a per kilowatt hour figure. But there seems to be the real possibility that the price of electricity generated, recovered and stored will be massive, even without government subsidies coming in year after year.

Ms Barnes: I think that’s for others to comment on. My focus is on getting the project at schedule and cost and making a business case for it, which I think is very strong. There are many other factors which will determine the price of electricity.

Senator Roberts: Minister, can you provide on notice the current projected cost per megawatt hour of electricity generated by Snowy 2.0 on the first year of operation, please?

Senator McAllister: Senator, I will take that on notice. I would also direct you to the evidence given to you already by Mr Barnes in relation both to the variability in the electricity market that Snowy will participate in but also—

Senator Roberts: A lot of variability means uncertainty.

Senator McAllister: Senator Roberts, I think that Mr Barnes has given an indication that he thinks it’s a strong business case and they’re presently working through it. I have taken your question on notice.

Senator Roberts: Thank you. This had nothing to do with your government, but right from the start of this project, Malcolm Turnbull’s government refused access to the cost-benefit analysis and heavily redacted the business case. There have been lots of questions about this project right from the start and now there are even more questions—and I don’t blame Mr Barnes for that.

Mr Barnes: My interest is running a commercially viable and efficient company, and that’s what I’ve done all of my career. The reason I joined Snowy was to get the opportunity to deliver Snowy 2, because I think it’s an incredibly important asset to the energy transition. I fully expect it to be very commercial. We’re trying to deal with the hardest part of the transition, which is providing deep storage to enable more renewables. So I expect it to be a very commercial business.

Senator Roberts: Can I confirm media reports that Snowy Hydro was found in a third independent audit last year to be noncompliant on environmental plans in 15 instances and that you have at last 10 management plans overdue?

Mr Barnes: I think, Senator, that you’re maybe referring to a National Parks Association report that was released last Thursday, without consultation with Snowy Hydro. We are currently operating under all of our construction approvals. So there are no breaches there. The plans and requirements as a result of the construction and operation of Snowy 2 obviously changed in nature over time. There are some that are relevant to construction, and we’re fully compliant with those. There are some that are relevant to operation and some that are relevant to rehabilitation. We work closely with all of the agencies to make sure that they’re reviewed and consulted on in every thorough way. I think there’s been a misunderstanding of some of the dates on various websites. So I have reached out to the National Parks Association to help them understand how it operates.

Senator Roberts: So it’s a misunderstanding that 10 of the 16 management plans for multibillion-dollar pumped hydro projects are overdue by 31 months, as reported in the media, citing the National Parks Association? So you think they’ve got it wrong somewhere?

Mr Barnes: The plans that are being referred to are prepared by Snowy and they are reviewed by various agencies. In consultation with the agencies, some of the dates that were originally envisaged are not being met and, therefore, are phases of the project which are way into the future. One of the things that may be useful for us to do is to work with the various agencies to make that understanding of how this process works. I would have happily taken the National Parks Association through that process.

Senator Roberts: Okay; so they jumped the gun?

Mr Barnes: They didn’t consult with Snowy Hydro before releasing it to the media.

Senator Roberts: Can I go to your opening statement? You recently announced a one- to two-year delay.  That’s a heck of a range, 100 per cent—from minimum to major.

Mr Barnes: It’s a project that’s being constructed over more than one to two years. It’s been in construction a few years. I think it was appropriate to give a range until we do more work.

Senator Roberts: I appreciate your honesty. I am not questioning your honesty—and I appreciate that you have given us that figure. But, for the project, that’s a pretty big number. What was the original planned project duration?

Mr Barnes: It was before my time. Perhaps we’ll come back to you. We gave a notice to proceed in mid-2020 and power was expected in 2025-26.

Mr Whitby: First power was for 1 July 2025, from a notice to proceed from August 2020. So five years was the original—

Senator Roberts: So the delay is 20 per cent to 40 per cent?

Mr Barnes: That would be the simple maths.

Chair: Senator Roberts, I’ll get you to wind it up and share the call, if that’s okay?

Senator Roberts: Okay. You mentioned in your statement the combination of four factors. What are the four factors? I’ve been through your statement and I couldn’t see them.

Mr Barnes: In our advice to ministers and in our media release we identified the effects of COVID and bushfires on the mobilisation of the project, the effect of many global factors on the availability of skilled labour and also the costs of materials. There’s a lot of steel and concrete in the project. We’ve found that some elements of the design—as we’ve gone through the process of design—are, in some cases, more costly to complete. And finally, the site conditions, of which the Florence ground conditions are the most impactful, also includes things like additional eroding. They’re the four factors.

Senator Roberts: Good luck getting that machine out.

Mr Barnes: Thanks.

5 replies
  1. Mavis Cottrell
    Mavis Cottrell says:

    Climate change is a hoax. At the 15th International Conference on Climate Change a group of former NASA scientists came out saying that climate change is a hoax. A specialist shows on his graphs that NASA has been doctoring the world’s correct temperature figures for years to make the data look as though the earth is heating up. The facts are that it has been cooling since the 1990’s. All this wind and solar expenditure is designed to make people poor and control them to bring in a one world government. Australia has more than enough trees to make this country already negative to reductions of air pollution. We need more power stations based on coal. It is India and China who are the world’s biggest polluters.

  2. RickWill
    RickWill says:

    This shows how screwed Australians are on electricity prices. The government sanctioned theft from consumers to the owners of weather dependent generators of $55/MWh is now more than the cost of electricity before Rudd.

    All this money can be wasted on Snowy 2 to increase the level of theft and that makes this incredible waste of resources viable.

    It is certainly good to see Senator Roberts asking the difficult questions of these climate zealots. But the main economic issue for Snowy 2 is that it enables a higher level of theft. Even with the present $55/MWh of theft, it is no longer viable to build more intermittent capacity because it just gets curtailed more often. The biggest growth area in generation is rooftop solar and this has no exposure to the wholesale daily price swings. So without storage, it is not viable to build more grid scale wind and solar. Increasing storage enablers more theft.

    The point of attack should be on the theft. It is time to end the theft and let these useless machines die out.

    Think how many new coal plants could be built instead of wasting money on a project that is guaranteed to increase theft from consumers and enrich the owners of grid scale “renewables” like Malcolm Turnbull and family.

    • CJ
      CJ says:

      The Malcolm Turnbull and family involvement… who scrutinised that?

      No one.

      Funny that.

      It’s about time someone bothered.

  3. John McKerral
    John McKerral says:

    The Snowy Hydro 2 representative is an idiot. The unit cost of the electricity is of absolute importance in cost benefit analysis. If they are to sell the product on to the grid they will have to cover all of their costs and make a profit as well ! The cost per MWh is going to be huge. They will either go broke or charge the retailers the full cost.
    He seems very poorly informed for someone in his position.
    John